How do I split a cell in a schedule in Revit?

How do I split a column in Revit schedule?

You can split the Graphical Column Schedule by defining a maximum number of columns to display per segment. On the Properties palette, under the Graphics section, enter the number of columns for each segment. The schedule breaks into a new segment when that number of columns is met.

How do you cut a schedule in Revit?

Select the schedule from the sheet. Adjust it using the split icon on the side and the drag points at the column ends. Move the schedule columns so that the first column is in the desired location on the sheet, and the rest of the columns are outside of the titleblock. Place the schedule onto the next sheet.

How do I group a row in a schedule in Revit?

Group Column Headings in a Schedule

  1. Open a schedule view.
  2. In the group header rows, drag the cursor across the headings to group. …
  3. Click Modify Schedule/Quantities tab Headers panel Group, or right-click the selected headings, and click Group Headers. …
  4. Enter text in the new row as necessary.

How do I edit a schedule in Revit?

select a cell or column in the schedule body. Click (Insert) on the Columns panel to open the Select Fields dialog, which functions like the Fields tab of the Schedule Properties dialog. Add new schedule fields and adjust the field order as needed.

IT IS INTERESTING:  Question: How do I apply materials in AutoCAD?

How do you unsplit a schedule in Revit?

You can rejoin the sections of a split schedule on a sheet. When you select the schedule on a sheet, a 4-way arrow control displays in the upper left corner of each section of the schedule. Use this arrow control to drag and drop a section of the schedule over another section to join them.

How do I hide a column in Revit schedule?

select cells, then click (Delete Column). select cells in one or more rows and click (Delete Row). select a cell or column header, then click (Hide Columns).